Submit new inquiry for this projectInquiry #1: Page 18 of the special provisions in section 39-1.12E discusses pre-paving profilographing in order to determine must-grinds. Will an inertial profiler or a high-speed profiler be acceptable for this work?
Thank you
Inquiry submitted 04/04/2013
Response #1:Submitted for consideration.
Response posted 04/04/2013
Response #2:The project must be bid on as it exists on bid opening day. Of course, after contract approval, proposals for changes to the contract will always be considered, with the appropriate cost or credit.
Response posted 04/09/2013
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.