Inquiry #1: In review of Cal Trans Specification book 2010 it states Primavera software. Is Primavera software mandatory?
Inquiry submitted 04/25/2013

Response #1:Submitted for consideration.
Response posted 04/25/2013


Response #2:Bid per bid documents.
The schedule software must include the latest version of Primavera P6 for Windows or equal. Any proposed schedule software equal to Primavera P6 must be capable of:
1. Generating files that can be imported into Primavera P6
2. Comparing 2 schedules and providing reports of changes in activity ID, activity description, constraints, calendar assignments, durations, and logic ties
Response posted 04/30/2013




Inquiry #2: 1) Is this project "Buy American"?
2)PEMB panel specs call for three minor ribs between the major ribs.Can we use a panel with two minor ribs between the major ribs?
3)Will structural steel for PEMB need to be hot dipped galvanized?
4)Will colors for PEMB be picked from manufacturers standard colors?

Inquiry submitted 04/29/2013

Response #1:Submitted for consideration.
Response posted 04/30/2013




Inquiry #3: Is there a soils report available for the project? Does the contractor need to remove any of the rocks and/or soils at the back of the Sandhouse?
Inquiry submitted 04/30/2013

Response #1:Submitted for consideration.
Response posted 04/30/2013


Response #2:No soils report available for the project. The allowable soil values were based on CBC minimums and past projects. Excavation will only be required for footings, slabs and pavement
Response posted 05/06/2013




Inquiry #4: Is there an opportunity to substitute pre-engineered canopies for the the wash rack and material bin canopies?
Inquiry submitted 04/30/2013

Response #1:Submitted for consideration.
Response posted 04/30/2013


Response #2:Bid according to the special provisions and plans
Response posted 05/06/2013




Inquiry #5: Per the elevations for the Sandhouse shown on A2-1 and A2.2, there aren’t any louvers designed into the envelope of the building yet there is an exhaust fan. Are any louvers required for fresh air intake into the Sandhouse?
Inquiry submitted 04/30/2013

Response #1:The exhaust fan has a back draft damper that is included in the exhaust fan assembly. It is specified in the mechanical plans and specified in the mechanical portions of the special provisions.
Response posted 05/06/2013




Inquiry #6: Electrical Switchgear manufacturers are indicating that the new 400 amp 3 ph 4w main panel and disconnect needs to be a stand up section and not a wall hung unit. Please verify whether or not this is an acceptable solution.
Inquiry submitted 05/01/2013

Response #1:Submitted for Consideration.
Response posted 05/07/2013


Response #2:Bid per bid documents. Provide wall hung main panelboards and main disconnects.
Response posted 05/08/2013




Inquiry #7: Bid item # 4 "Roadway Excavation" - Where can we get the cross-sections for quantity calculation?
Inquiry submitted 05/02/2013

Response #1:Submitted for consideration.
Response posted 05/07/2013




Inquiry #8: Location of material bins (Building A-1)- Building location as shown on C-1 is different than shown on GP. Which is the correct building location?
Inquiry submitted 05/02/2013

Response #1:Submitted for consideration.
Response posted 05/07/2013


Response #2:The location shown on C-1 is the correct location.
Response posted 05/09/2013




Inquiry #9: Does Caltrans require the areas to receive new AC paving to be covered with slurry seal?
Inquiry submitted 05/02/2013

Response #1:Submitted for consideration.
Response posted 05/07/2013


Response #2:Only the existing pavement will be slurry sealed.
Response posted 05/09/2013




Inquiry #10: Please confirm the material type of the window frames in the Sand House. The plans appear to be Hollow Metal and the specifications call for aluminum.
Inquiry submitted 05/03/2013

Response #1:Submitted for consideration.
Response posted 05/07/2013


Response #2:Please bid per the project's plans and specifications.
Response posted 05/08/2013




Inquiry #11: Please confirm if the underside of the structures are to be field painted.
Inquiry submitted 05/06/2013

Response #1:Submitted for consideration.
Response posted 05/07/2013


Response #2:Only the bottom of the decking at the washrack needs to be field painted.
Response posted 05/09/2013




Inquiry #12: Please confirm the location of concrete surfaces that require the water repellant coating (99-07182).
Inquiry submitted 05/06/2013

Response #1:Submitted for consideration.
Response posted 05/07/2013


Response #2:As per the special provisions, the water repellent coating shall be applied to all exterior concrete surfaces.
Response posted 05/08/2013




Inquiry #13: On sheet ST2-0 (Project Design Criteria) there is reference to 2007 CBC or 2006 IBC and under seismic Loads the Ss= 0.3562 (USGS has Fawnskin listed at .1832) S1= 0.1759 (USGS has Fawnskin listed at .0745) Please clarify correct load requirement as this effects the design and ultimately the price.


Inquiry submitted 05/07/2013

Response #1:Submitted for consideration
Response posted 05/08/2013




Inquiry #14: Will you consider extending the Bid Due date Due to the number on unanswered RFI- 1 day prior to bid date?
Inquiry submitted 05/08/2013

Response #1:Submitted for consideration.
Response posted 05/08/2013


Response #2:Bid Opening as scheduled on 05/09/2013.
Response posted 05/08/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.