Caltrans Office Engineer

Viewing inquiries for 06-0Q3604

Submit new inquiry for this project


Inquiry #1: Contract allocates only 25 working days to complete project. Due to the 1.5 mile lane closure restriction and the amount of time needed to complete the CIPR work along with the supplemental compaction. Project cannot be completed in 25 working days. Will additional working days be granted via an addendum?
Inquiry submitted 04/03/2013

Response #1:Submitted for consideration.
Response posted 04/04/2013


Response #2:No additional working days will be granted.
Response posted 04/08/2013




Inquiry #2: Sheet X-1 of the project plans shows cross section of roadway with an overlay of 0.15' HMA (Type A). Typicals on the same plan sheet and legend show a section of 0.10 HMA (Type A). Which is correct?
Inquiry submitted 04/03/2013

Response #1:Submitted for consideration.
Response posted 04/04/2013


Response #2:Sheet X-1 of the project plans shows cross section of roadway with an overlay of 0.15' HMA (Type A) is the correct thickness.
Response posted 04/08/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.