Inquiry #1: How is Caltrans going to pay for the removal the of existing Fiber Weed Mat under the Metal Beam Guard Railing.
Inquiry submitted 04/05/2013

Response #1:4/8/13: Your inquiry is under review. Please note that due to the current time frame between the inquiry submittal and the bid opening date, a response may not be provided before the bid opening. If a response is not provided before the bid opening addressing your concern, please bid per the current contract documents. Thank you for your patience.

Response posted 04/08/2013




Inquiry #2: The Special Provisions state that the existing polyester concrete overlay must be removed by diamond grinding. This equipment will not be able to remove the existing overlay closer than 18-inches from the concrete barrier. Will Caltrans consider or recommend alternate removal methods for the remaining, unreachable overlay?
Inquiry submitted 04/08/2013

Response #1:4/8/13: Your inquiry is under review. Please note that due to the current time frame between the inquiry submittal and the bid opening date, a response may not be provided before the bid opening. If a response is not provided before the bid opening addressing your concern, please bid per the current contract documents. Thank you for your patience.
Response posted 04/08/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.