EA Route Post Mile Name Program Work Description Project Manager
09-21340 395 30.8 / 41.8 Olancha/Cartago Four-Lane STIP Upgrade existing two-lane highway to a four-lane expressway. Cedrik Zemitis
(760) 872-5250
09-2144U 395 65.2 / 71.2
Manzanar/Independence Four-Lane STIP Upgrade existing two-lane highway to a four-lane expressway. Tom Meyers
(760) 872-5214
09-21461 395 77.3 / 91.6 Black Rock Four-Lane STIP Upgrade existing two-lane highway to a four-lane expressway. Tom Meyers
(760) 872-5214
09-25801 395 117.9 / 122.4 Ed Powers Rehab SHOPP Rehabilitate roadway, widen shoulders, and construct sidewalk. Cedrik Zemitis
(760) 872-5250
09-26901 395 R128.6/R129.5 South Sherwin Summit Rehab SHOPP Rehabilitate roadway and widen shoulders. Cedrik Zemitis
(760) 872-5250
09-28750 190 65.9/66.5 Towne Pass Rockfall SHOPP Realign roadway to address rockfall. Cedrik Zemitis
(760) 872-5250
09-31450 395 17.9 / Coso Safety Roadside Rest Area Rehab SHOPP Upgrade and repair existing safety roadside rest area making it ADA compliant. Tom Meyers
(760) 872-5214
09-31660 395 R8.6 / R11.8 North Little Lake Rehab SHOPP Rehabilitate roadway, widen shoulders and realign curve. Cedrik Zemitis
(760) 872-5250
09-31810 190 87.6/88.3 Sand Dunes Scenic Pullout STIP-TE Construct turning lane, parking area, and other amenities. Tom Meyers
(760) 872-5214
09-33380 190 47.4 Father Crowley Point Scenic Viewpoint STIP-TE Construct paved parking area and other improvements. Tom Meyers
(760) 872-5214
09-33650 395 57.0/57.9 Lone Pine CAPM SHOPP Pavement rehabilitation. Cedrik Zemitis
(760) 872-5250