LAS-395 HONEY LAKE SAFETY ROADSIDE REST AREA (02-4E690)
Photo

Description: In Lassen County, SR395, PM 49.50, rehabilitate water and sewer system.
Project Manager: Eric Orr

   
   

LAS-36 WESTWOOD RAILROAD CROSSING IMPROVEMENT  (02-4G740) Photo

Description: In Lassen County, Hwy 36, PM3.4, Vertical curve correction to fix uneven pavement due to grade change at-grade railroad crossing. Scope includes new profile of roadway throughout the project.
Construction estimated to begin September 2014.
Project Manager: Eric Orr

   
   

LAS-139 GRASSHOPPER CHIP SEAL  (02-4F130)

   
   

LAS-395 AR MILFORD PHASE 1 CHIP SEAL  (02-4G140)

Description: In Lassen County, SR395, PM 24.7/41.5, Near Doyle from Willow Ranch Creek Bridge to 0.2 miles south Laufman Engineer Station Road. Micro-surfacing.
Construction estimated to begin November 2014.
Project Manager: Lance Brown

   
   

LAS-395 JOHNSTONVILLE ROADWAY REHABILITATION  (02-3C071) Photo

Description: In Lassen County, SR395, PM 61.0/76.6, At and near Johnstonville from 0.4 mile south of Bangham Lane to 0.3 mile south of Wendel Road, Roadway Rehabilitation. Construction estimated to begin April 2014.
Project Manager: Eric Orr

   
   

LAS-VAR BRIDGE MAINTENANCE  (02-3E630) Photo

Description: In Lassen County, at various locations. Structure work at each location may include: removal of existing AC overlay, repair of unsound concrete, sealing deck with methacrylate, placing polyester concrete or AC overlay (w/ membrane), modifying bridge barriers, cleaning joints and installing joint seals, etc. Existing white and yellow striping will come up with AC on decks with AC overlays, or be ground off of bare PCC decks. All work will be confined to the bridge decks, approach/departure roadways and MBGR areas.
Construction estimated to be completed February 2014.
Project Manager: Lance Brown