DAY CLOSURES MONDAY 10/06/2008 [24 Closures Found]
Rte Dir Lanes
Closed
Total
Lanes
Begin - End Location/
Type of Work
Closure
Period
1 NB #2 2 8TH AVE RT - 10 TH AVE RT OID 10/06 09:01
landscaping 10/06 15:01
1 NB/SB #2 2 EMERALD BAY ENT #1&2 - EMERALD BAY ENT #7 LT 10/06 09:01
Sewer Repair 10/06 15:01
1 SB #2 2 5TH AVE RT - 8TH AVE RT 10/06 09:01
Move Equipment 10/06 15:01
5 EB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/06 09:01
Tree Trimming 10/06 15:01
5 EB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/06 09:01
Tree Trimming 10/06 15:01
5 NB/SB #1 2 NB OFF TO JUNIPERO SERRA - SB OFF TO JUNIPERO SERRA 10/06 09:01
Paving 10/07 05:01
5 SB #1 2 SB OFF HOV TO GENE A WAY - SB ON HOV FR GENE A. WAY 10/06 09:01
Tree Trimming 10/06 15:01
5 SB #5 5 EL CAMINO REAL UC 55-203 - EL CAMINO REAL UC 55-203 10/06 11:15
Guardrail Repair 10/06 14:01
5 SB #3 3 SB OFF TO MAGNOLIA AVE - SB OFF TO MAGNOLIA AVE 10/06 09:01
Sign Installation 10/06 15:01
5 SB #3 3 SB OFF TO MAGNOLIA AVE - SB OFF TO MAGNOLIA AVE 10/06 09:01
Sign Installation 10/06 15:01
5 SB #1 2 SB OFF HOV TO GENE A WAY - SB ON HOV FR GENE A. WAY 10/06 09:01
Tree Trimming 10/06 15:01
5 WB #3 3 NB ON FR SAND CYN AVE - SB OFF TO SAND CYN AVE 10/06 09:15
Other check Remarks 10/06 15:15
5 WB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/06 09:01
Tree Trimming 10/06 15:01
22 EB #2 2 JCT 5 - EB OFF TO NB 5 / NB 57 10/06 09:01
Other check Remarks 10/06 14:01
39 SB #1 3 ATLANTA AVE - JCT ST 1 10/06 09:15
Move Equipment 10/06 15:15
55 EB/WB #1 4 Slope Paving at Paularino - Slope Paving at Paularino 10/06 09:01
Bridge Work 10/06 14:01
55 SB #1 2 SB OFF MCFADDEN/VILLAGE - SB OFF MCFADDEN/VILLAGE 10/06 10:01
Paving 10/06 14:01
57 SB #2 2 SB ON LAMBERT RD - LAMBERT RD UC 55-492 10/06 08:01
Drainage 10/06 15:01
57 SB #1 3 SB OFF LAMBERT RD - SB OFF LAMBERT RD 10/06 08:01
Paving 10/06 15:01
57 SB #1 3 END BR 55-492 - SB ON LAMBERT RD 10/06 08:01
Paving 10/06 14:01
133 NB #2 3 EL TORO RD RT - RAMP LT FR SB RTE 73 10/06 09:01
Electrical Repair 10/06 15:01
405 NB/SB Left HOV, Median 6 SB OFF TO BAKE PARKWAY - BEAR ST OC 55-433 10/06 09:01
Sweeping 10/06 15:01


NIGHT CLOSURES MONDAY 10/06/2008 [27 Closures Found]
Rte Dir Lanes
Closed
Total
Lanes
Begin - End Location/
Type of Work
Closure
Period
1 NB #1 2 NB OFF TO DOHENY PK RD - DEL OBISPO ST 10/06 20:30
Paving 10/07 05:30
5 EB/WB #1, #2, #3 3 NB ON FR ANAHEIM BLVD - SB OFF TO DISNEY WAY 10/06 21:01
Electrical Repair 10/07 05:01
5 NB #1, #2, #3, Left HOV 5 TUSTIN RNCH RD OC 55-657 - FIRST STREET OC 55-174 10/06 23:01
Bridge Work 10/07 04:01
5 NB #1, #2, #3 3 JCT 91 / 5 SEP OH 55-502R - ARTESIA AVE UC 55-139 10/06 23:30
Striping / Marking 10/07 04:01
5 NB #1, Left HOV 5 NB OFF TO CHAPMAN AVE - NB OFF TO CHAPMAN AVE 10/06 22:01
Other check Remarks 10/07 04:01
5 NB #1, #2, Left HOV 5 BROOKHURST ST OC 55-89R - JCT 91 / 5 SEP OH 55-293L 10/06 22:01
Bridge Work 10/07 05:01
5 NB #1 1 NB ON FR ORANGETHORPE AV - NB ON FR ORANGETHORPE AV 10/06 23:01
Electrical Repair 10/07 05:01
5 NB #1, #2, #3, Left HOV 5 RED HILL AVE UC 55-193 - FIRST STREET OC 55-174 10/06 23:01
Bridge Work 10/07 04:01
5 NB #1 1 NB ON FR MANCHESTER / BCH - NB ON FR MANCHESTER / BCH 10/06 23:01
Electrical Repair 10/07 05:01
5 NB/SB #2 2 NB OFF TO JUNIPERO SERRA - SB OFF TO JUNIPERO SERRA 10/06 21:01
Paving 10/07 05:01
5 SB #1, #2 2 SB ON FR BEACH BLVD - SB ON FR BEACH BLVD 10/06 23:01
K-Rail 10/07 05:01
5 SB #1, #2 2 SB ON ARTESIA AVE - SB ON ARTESIA AVE 10/06 23:01
K-Rail 10/07 05:01
5 SB #1, #2 2 SB OFF TO BEACH BLVD - SB OFF TO BEACH BLVD 10/06 23:01
K-Rail 10/07 05:01
5 SB #1, #2 2 SB ON FR BEACH BLVD - SB ON FR BEACH BLVD 10/06 23:01
K-Rail 10/07 05:01
5 SB #1, #2, #3, Left HOV 5 FIRST STREET OC 55-174 - TUSTIN RNCH RD OC 55-657 10/06 23:01
Bridge Work 10/07 04:01
5 SB #1, #2, #3 3 SB ON ARTESIA AVE - JCT 91 / 5 SEP OH 55-502R 10/06 23:01
Bridge Work 10/07 04:01
22 WB #2 3 EB OFF BRISTOL/LA VETA - EB OFF BRISTOL/LA VETA 10/06 22:15
Street Rehab 10/07 05:15
39 NB/SB #1, #2, #3 4 SLATER AVE Lanes 1, 2, 4; 200 ft away from intersection - SLATER AVE Lanes 1, 2, 4; 200 ft away from intersection 10/06 22:01
Electrical Repair 10/07 05:01
57 SB #1, #2 2 SB ON LAMBERT RD - LAMBERT RD UC 55-492 10/06 21:01
Paving 10/07 05:01
57 SB #1, #2 2 SB OFF LAMBERT RD - SB OFF LAMBERT RD 10/06 21:01
Paving 10/07 05:01
90 EB/WB #1 2 RANDOLPH AVE LT - BERRY ST LT / JASMINE DR 10/06 22:01
Survey 10/07 05:01
90 EB/WB #1 2 RANDOLPH AVE LT - BERRY ST LT / JASMINE DR 10/06 22:01
Survey 10/07 05:01
91 WB #1, #2 2 WB 91 CONNECTOR TO NB RTE 5 - WB 91 CONNECTOR TO NB RTE 5 10/06 23:01
Bridge Work 10/07 04:01
261 SB #1, #2 2 SB ON FR TOLL PLAZA - SB ON FR TOLL PLAZA 10/06 21:01
Marker Replacement 10/07 05:01
261 SB #1, #2 2 JCT RTE 241 - BEGIN RTE AT WALNUT OC 10/06 21:01
Marker Replacement 10/07 05:01
261 SB #1, #2 2 SB ON FR IRVINE BLVD - SB ON FR IRVINE BLVD 10/06 21:01
Marker Replacement 10/07 05:01
261 SB #1, #2 2 SB ON FR SANTIAGO CNYN - SB ON FR SANTIAGO CNYN 10/06 21:01
Marker Replacement 10/07 05:01


DAY CLOSURES TUESDAY 10/07/2008 [21 Closures Found]
Rte Dir Lanes
Closed
Total
Lanes
Begin - End Location/
Type of Work
Closure
Period
1 NB #2 2 8TH AVE RT - 10 TH AVE RT OID 10/07 09:01
landscaping 10/07 15:01
1 NB/SB #2 2 EMERALD BAY ENT #1&2 - EMERALD BAY ENT #7 LT 10/07 09:01
Sewer Repair 10/07 15:01
1 SB #2 2 5TH AVE RT - 8TH AVE RT 10/07 09:01
Move Equipment 10/07 15:01
5 EB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/07 09:01
Tree Trimming 10/07 15:01
5 EB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/07 09:01
Tree Trimming 10/07 15:01
5 NB/SB #1 2 NB OFF TO JUNIPERO SERRA - SB OFF TO JUNIPERO SERRA 10/07 09:01
Paving 10/08 05:01
5 SB #1 2 SB OFF HOV TO GENE A WAY - SB ON HOV FR GENE A. WAY 10/07 09:01
Tree Trimming 10/07 15:01
5 SB #1 2 SB OFF HOV TO GENE A WAY - SB ON HOV FR GENE A. WAY 10/07 09:01
Tree Trimming 10/07 15:01
5 WB #3 3 NB ON FR SAND CYN AVE - SB OFF TO SAND CYN AVE 10/07 09:15
Other check Remarks 10/07 15:15
5 WB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/07 09:01
Tree Trimming 10/07 15:01
22 EB #2 2 JCT 5 - EB OFF TO NB 5 / NB 57 10/07 09:01
Other check Remarks 10/07 14:01
39 NB/SB #1, #2, #3 3 ROSECRANS AVE - IMPERIAL HWY (RTE 90) 10/07 09:01
Other check Remarks 10/07 15:30
39 SB #1 3 ATLANTA AVE - JCT ST 1 10/07 09:15
Move Equipment 10/07 15:15
55 EB/WB #1 4 Slope Paving at Paularino - Slope Paving at Paularino 10/07 09:01
Bridge Work 10/07 14:01
55 SB #2 2 SB OFF MCFADDEN/VILLAGE - SB OFF MCFADDEN/VILLAGE 10/07 10:01
Paving 10/07 14:01
57 SB #2 2 SB ON LAMBERT RD - LAMBERT RD UC 55-492 10/07 08:01
Drainage 10/07 15:01
57 SB #1 3 SB OFF LAMBERT RD - SB OFF LAMBERT RD 10/07 08:01
Paving 10/07 15:01
57 SB #1 3 END BR 55-492 - SB ON LAMBERT RD 10/07 08:01
Paving 10/07 14:01
241 SB #1, #2, #3 3 SB OFF TO S MARGARITA P - SB OFF TO S MARGARITA P 10/07 09:01
Striping / Marking 10/07 14:01


NIGHT CLOSURES TUESDAY 10/07/2008 [32 Closures Found]
Rte Dir Lanes
Closed
Total
Lanes
Begin - End Location/
Type of Work
Closure
Period
1 NB #1 2 NB OFF TO DOHENY PK RD - DEL OBISPO ST 10/07 20:30
Paving 10/08 05:30
5 EB/WB #1, #2, #3 3 NB ON FR ANAHEIM BLVD - SB OFF TO DISNEY WAY 10/07 21:01
Electrical Repair 10/08 05:01
5 NB #1, #2, Left HOV 5 BROOKHURST ST OC 55-89R - JCT 91 / 5 SEP OH 55-293L 10/07 22:01
Bridge Work 10/08 05:01
5 NB #1 1 NB ON FR ORANGETHORPE AV - NB ON FR ORANGETHORPE AV 10/07 23:01
Electrical Repair 10/08 05:01
5 NB #1 1 NB ON FR MANCHESTER / BCH - NB ON FR MANCHESTER / BCH 10/07 23:01
Electrical Repair 10/08 05:01
5 NB #1, Left HOV 5 NB OFF TO CHAPMAN AVE - NB OFF TO CHAPMAN AVE 10/07 22:01
Other check Remarks 10/08 04:01
5 NB #1, #2, #3 3 JCT 91 / 5 SEP OH 55-502R - ARTESIA AVE UC 55-139 10/07 23:30
Striping / Marking 10/08 04:01
5 NB/SB #2 2 NB OFF TO JUNIPERO SERRA - SB OFF TO JUNIPERO SERRA 10/07 21:01
Paving 10/08 05:01
5 SB #1, #2 2 SB ON ARTESIA AVE - SB ON ARTESIA AVE 10/07 23:01
K-Rail 10/08 05:01
5 SB #1, #2, #3 3 SB ON ARTESIA AVE - JCT 91 / 5 SEP OH 55-502R 10/07 23:01
Bridge Work 10/08 04:01
5 SB #1, #2 2 SB OFF TO BEACH BLVD - SB OFF TO BEACH BLVD 10/07 23:01
K-Rail 10/08 05:01
5 SB #1, #2 2 SB ON FR BEACH BLVD - SB ON FR BEACH BLVD 10/07 23:01
K-Rail 10/08 05:01
5 SB #1, #2, #3, Left HOV 5 FIRST STREET OC 55-174 - TUSTIN RNCH RD OC 55-657 10/07 23:01
Bridge Work 10/08 04:01
5 SB #1, #2 2 SB OFF CARLOTA / VALENCIA - E.B. UC 55-235 10/07 23:01
Paving 10/08 05:01
22 EB #1, #2 2 EB OFF TO NB 5 / NB 57 - EB OFF TO NB 5 / NB 57 10/08 00:01
Other check Remarks 10/08 05:01
22 WB #1, #2 2 WB OFF TO NB 5 / NB 57 - WB OFF TO NB 5 / NB 57 10/08 00:01
Other check Remarks 10/08 05:01
22 WB #2 3 EB OFF BRISTOL/LA VETA - EB OFF BRISTOL/LA VETA 10/07 22:15
Street Rehab 10/08 05:15
39 NB/SB #1, #2, #3 4 SLATER AVE Lanes 1, 2, 4; 200 ft away from intersection - SLATER AVE Lanes 1, 2, 4; 200 ft away from intersection 10/07 22:01
Electrical Repair 10/08 05:01
57 SB #1, #2 2 SB ON LAMBERT RD - LAMBERT RD UC 55-492 10/07 21:01
Paving 10/08 05:01
57 SB #1, #2 2 SB OFF LAMBERT RD - SB OFF LAMBERT RD 10/07 21:01
Paving 10/08 05:01
73 NB #2 3 JCT 73/405 - JCT 73/405 10/07 22:01
Other check Remarks 10/08 05:01
90 EB/WB #1 2 RANDOLPH AVE LT - HARBOR BLVD 10/07 22:01
Survey 10/08 05:01
91 WB #1, #2 2 WB 91 CONNECTOR TO NB RTE 5 - WB 91 CONNECTOR TO NB RTE 5 10/07 23:01
Bridge Work 10/08 04:01
261 SB #1, #2 2 SB ON FR SANTIAGO CNYN - SB ON FR SANTIAGO CNYN 10/07 21:01
Marker Replacement 10/08 05:01
261 SB #1, #2 2 SB ON FR TOLL PLAZA - SB ON FR TOLL PLAZA 10/07 21:01
Marker Replacement 10/08 05:01
261 SB #1, #2 2 JCT RTE 241 - BEGIN RTE AT WALNUT OC 10/07 21:01
Marker Replacement 10/08 05:01
261 SB #1, #2 2 SB ON FR IRVINE BLVD - SB ON FR IRVINE BLVD 10/07 21:01
Marker Replacement 10/08 05:01
405 NB #1, #2 3 SB ON SEG FR FAIRVIEW Fairview Offramp - SB OFF TO FAIRVIEW RD 10/07 22:01
Other check Remarks 10/08 05:01
405 NB #4, #5, #6 8 SB ON SEG FR FAIRVIEW - SB OFF TO FAIRVIEW RD 10/07 22:01
Other check Remarks 10/08 05:01
405 NB #1, #2, #3 3 SB ON SEG FR FAIRVIEW Harbor/Susan St. Off ramp - SB OFF TO FAIRVIEW RD 10/07 22:01
Other check Remarks 10/08 05:01
405 SB #1, #2, Left HOV 3 SB ON SEG FR FAIRVIEW - SB OFF TO FAIRVIEW RD 10/07 22:01
Other check Remarks 10/08 05:01


DAY CLOSURES WEDNESDAY 10/08/2008 [18 Closures Found]
Rte Dir Lanes
Closed
Total
Lanes
Begin - End Location/
Type of Work
Closure
Period
1 NB/SB #2 2 EMERALD BAY ENT #1&2 - EMERALD BAY ENT #7 LT 10/08 09:01
Sewer Repair 10/08 15:01
1 SB #2 2 5TH AVE RT - 8TH AVE RT 10/08 09:01
Move Equipment 10/08 15:01
5 EB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/08 09:01
Tree Trimming 10/08 15:01
5 EB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/08 09:01
Tree Trimming 10/08 15:01
5 NB/SB #1 2 NB OFF TO JUNIPERO SERRA - SB OFF TO JUNIPERO SERRA 10/08 09:01
Paving 10/09 05:01
5 SB #1 2 SB OFF HOV TO GENE A WAY - SB ON HOV FR GENE A. WAY 10/08 09:01
Tree Trimming 10/08 15:01
5 SB #1 2 SB OFF HOV TO GENE A WAY - SB ON HOV FR GENE A. WAY 10/08 09:01
Tree Trimming 10/08 15:01
5 WB #3 3 NB ON FR SAND CYN AVE - SB OFF TO SAND CYN AVE 10/08 09:15
Other check Remarks 10/08 15:15
5 WB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/08 09:01
Tree Trimming 10/08 15:01
22 EB #2 2 JCT 5 - EB OFF TO NB 5 / NB 57 10/08 09:01
Other check Remarks 10/08 14:01
39 NB/SB #1, #2, #3 3 ROSECRANS AVE - IMPERIAL HWY (RTE 90) 10/08 09:01
Other check Remarks 10/08 15:30
39 SB #1 3 ATLANTA AVE - JCT ST 1 10/08 09:15
Move Equipment 10/08 15:15
55 EB/WB #1 4 Slope Paving at Paularino - Slope Paving at Paularino 10/08 09:01
Bridge Work 10/08 14:01
57 NB Left HOV 5 BEG SB INDEP ALIGN LT @ - BALL RD OC 55-524 10/08 09:01
Striping / Marking 10/08 14:30
57 SB #1 3 END BR 55-492 - SB ON LAMBERT RD 10/08 08:01
Paving 10/08 14:01
57 SB #2 2 SB ON LAMBERT RD - LAMBERT RD UC 55-492 10/08 08:01
Drainage 10/08 15:01


NIGHT CLOSURES WEDNESDAY 10/08/2008 [34 Closures Found]
Rte Dir Lanes
Closed
Total
Lanes
Begin - End Location/
Type of Work
Closure
Period
1 NB #1 2 NB OFF TO DOHENY PK RD - DEL OBISPO ST 10/08 20:30
Paving 10/09 05:30
5 EB/WB #1, #2, #3 3 NB ON FR ANAHEIM BLVD - SB OFF TO DISNEY WAY 10/08 21:01
Electrical Repair 10/09 05:01
5 NB #1, #2 2 NB OFF TO RED HILL AVE - NB OFF TO RED HILL AVE 10/08 22:01
Bridge Work 10/09 04:01
5 NB #1, #2, Left HOV 5 NB OFF TO CHAPMAN AVE - NB OFF TO CHAPMAN AVE 10/08 22:01
Other check Remarks 10/09 04:01
5 NB #1, #2, #3 3 JCT 91 / 5 SEP OH 55-502R - ARTESIA AVE UC 55-139 10/08 23:30
Striping / Marking 10/09 04:01
5 NB #1, #2, Left HOV 5 BROOKHURST ST OC 55-89R - JCT 91 / 5 SEP OH 55-293L 10/08 22:01
Bridge Work 10/09 05:01
5 NB #1 1 NB ON FR MANCHESTER / BCH - NB ON FR MANCHESTER / BCH 10/08 23:01
Electrical Repair 10/09 05:01
5 NB #1 1 NB OFF TO SB RTE 55 - NB OFF TO SB RTE 55 10/08 22:01
Bridge Work 10/09 04:01
5 NB #1 1 NB ON FR ORANGETHORPE AV - NB ON FR ORANGETHORPE AV 10/08 23:01
Electrical Repair 10/09 05:01
5 NB #3, #4, #5 5 END BR 55-655 - FIRST STREET OC 55-174 10/08 23:01
Bridge Work 10/09 04:01
5 NB/SB #2 2 NB OFF TO JUNIPERO SERRA - SB OFF TO JUNIPERO SERRA 10/08 21:01
Paving 10/09 05:01
5 SB #1, #2, #3 3 SB ON ARTESIA AVE - JCT 91 / 5 SEP OH 55-502R 10/08 23:01
Bridge Work 10/09 04:01
5 SB #1, #2 2 SB ON ARTESIA AVE - SB ON ARTESIA AVE 10/08 23:01
K-Rail 10/09 05:01
5 SB #1, #2 2 SB ON FR BEACH BLVD - SB ON FR BEACH BLVD 10/08 23:01
K-Rail 10/09 05:01
5 SB #1, #2 2 SB OFF TO BEACH BLVD - SB OFF TO BEACH BLVD 10/08 23:01
K-Rail 10/09 05:01
22 EB #1, #2 2 EB OFF TO NB 5 / NB 57 - EB OFF TO NB 5 / NB 57 10/09 00:01
Other check Remarks 10/09 05:01
22 WB #2 3 EB OFF BRISTOL/LA VETA - EB OFF BRISTOL/LA VETA 10/08 22:15
Street Rehab 10/09 05:15
22 WB #1, #2 2 WB OFF TO NB 5 / NB 57 - WB OFF TO NB 5 / NB 57 10/09 00:01
Other check Remarks 10/09 05:01
39 NB/SB #1, #2, #3 4 SLATER AVE Lanes 1, 2, 4; 200 ft away from intersection - SLATER AVE Lanes 1, 2, 4; 200 ft away from intersection 10/08 22:01
Electrical Repair 10/09 05:01
57 SB #1, #2 2 SB ON LAMBERT RD - LAMBERT RD UC 55-492 10/08 21:01
Paving 10/09 05:01
57 SB #1, #2 2 SB OFF LAMBERT RD - SB OFF LAMBERT RD 10/08 21:01
Paving 10/09 05:01
73 NB #2 3 JCT 73/405 - JCT 73/405 10/08 22:01
Other check Remarks 10/09 05:01
90 EB/WB #1 2 RANDOLPH AVE LT - HARBOR BLVD 10/08 22:01
Survey 10/09 05:01
90 EB/WB #1 2 RANDOLPH AVE LT - HARBOR BLVD 10/08 22:01
Survey 10/09 05:01
91 WB #1, #2 2 WB 91 CONNECTOR TO NB RTE 5 - WB 91 CONNECTOR TO NB RTE 5 10/08 23:01
Bridge Work 10/09 04:01
261 SB #1, #2 2 JCT RTE 241 - BEGIN RTE AT WALNUT OC 10/08 21:01
Marker Replacement 10/09 05:01
261 SB #1, #2 2 SB ON FR SANTIAGO CNYN - SB ON FR SANTIAGO CNYN 10/08 21:01
Marker Replacement 10/09 05:01
261 SB #1, #2 2 SB ON FR TOLL PLAZA - SB ON FR TOLL PLAZA 10/08 21:01
Marker Replacement 10/09 05:01
261 SB #1, #2 2 SB ON FR IRVINE BLVD - SB ON FR IRVINE BLVD 10/08 21:01
Marker Replacement 10/09 05:01
405 NB #1, #2, #3 3 SB ON SEG FR FAIRVIEW Harbor/Susan St Off Ramp - SB OFF TO FAIRVIEW RD 10/08 22:01
Other check Remarks 10/09 05:01
405 NB #4, #5, #6 8 SB ON SEG FR FAIRVIEW - SB OFF TO FAIRVIEW RD 10/08 22:01
Other check Remarks 10/09 05:01


DAY CLOSURES THURSDAY 10/09/2008 [20 Closures Found]
Rte Dir Lanes
Closed
Total
Lanes
Begin - End Location/
Type of Work
Closure
Period
1 NB/SB #2 2 EMERALD BAY ENT #1&2 - EMERALD BAY ENT #7 LT 10/09 09:01
Sewer Repair 10/09 15:01
1 NB/SB #2 2 ALISO PED OC 55-27 - ALISO PED OC 55-27 10/09 09:01
Bridge Work 10/09 14:01
1 SB #2 2 5TH AVE RT - 8TH AVE RT 10/09 09:01
Move Equipment 10/09 15:01
5 EB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/09 09:01
Tree Trimming 10/09 15:01
5 EB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/09 09:01
Tree Trimming 10/09 15:01
5 N/A #3 3 OSO PARKWAY OC 55-509 - OSO PARKWAY OC 55-509 10/09 09:01
Other check Remarks 10/09 15:01
5 NB/SB #1 2 NB OFF TO JUNIPERO SERRA - SB OFF TO JUNIPERO SERRA 10/09 09:01
Paving 10/10 05:01
5 SB #1 2 SB OFF HOV TO GENE A WAY - SB ON HOV FR GENE A. WAY 10/09 09:01
Tree Trimming 10/09 15:01
5 SB #1 2 SB OFF HOV TO GENE A WAY - SB ON HOV FR GENE A. WAY 10/09 09:01
Tree Trimming 10/09 15:01
5 WB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/09 09:01
Tree Trimming 10/09 15:01
5 WB #3 3 NB ON FR SAND CYN AVE - SB OFF TO SAND CYN AVE 10/09 09:15
Other check Remarks 10/09 15:15
22 EB #2 2 JCT 5 - EB OFF TO NB 5 / NB 57 10/09 09:01
Other check Remarks 10/09 14:01
39 NB/SB #1, #2, #3 3 ROSECRANS AVE - IMPERIAL HWY (RTE 90) 10/09 09:01
Other check Remarks 10/09 15:30
39 SB #1 3 ATLANTA AVE - JCT ST 1 10/09 09:15
Move Equipment 10/09 15:15
55 EB/WB #1 4 Slope Paving at Paularino - Slope Paving at Paularino 10/09 09:01
Bridge Work 10/09 14:01
57 NB Left HOV 5 BEG SB INDEP ALIGN LT @ - BALL RD OC 55-524 10/09 09:01
Striping / Marking 10/09 14:30
57 SB #2 2 SB ON LAMBERT RD - LAMBERT RD UC 55-492 10/09 08:01
Drainage 10/09 15:01
57 SB #1 3 SB OFF LAMBERT RD - SB OFF LAMBERT RD 10/09 08:01
Paving 10/09 15:01
57 SB #1 3 END BR 55-492 - SB ON LAMBERT RD 10/09 08:01
Paving 10/09 14:01


NIGHT CLOSURES THURSDAY 10/09/2008 [34 Closures Found]
Rte Dir Lanes
Closed
Total
Lanes
Begin - End Location/
Type of Work
Closure
Period
1 NB #1 2 NB OFF TO DOHENY PK RD - DEL OBISPO ST 10/09 20:30
Paving 10/10 05:30
5 EB/WB #1, #2, #3 3 NB ON FR ANAHEIM BLVD - SB OFF TO DISNEY WAY 10/09 21:01
Electrical Repair 10/10 05:01
5 NB #1 1 NB ON FR MANCHESTER / BCH - NB ON FR MANCHESTER / BCH 10/09 23:01
Electrical Repair 10/10 05:01
5 NB #1 1 NB ON FR ORANGETHORPE AV - NB ON FR ORANGETHORPE AV 10/09 23:01
Electrical Repair 10/10 05:01
5 NB #1, #2, Left HOV 5 NB OFF TO CHAPMAN AVE - NB OFF TO CHAPMAN AVE 10/09 22:01
Other check Remarks 10/10 04:01
5 NB #1 1 NB ON FR MANCHESTER / BCH - NB ON FR MANCHESTER / BCH 10/09 23:01
Electrical Repair 10/10 05:01
5 NB #1, #2, Left HOV 5 BROOKHURST ST OC 55-89R - JCT 91 / 5 SEP OH 55-293L 10/09 22:01
Bridge Work 10/10 05:01
5 NB #1, #2, #3 3 JCT 91 / 5 SEP OH 55-502R - ARTESIA AVE UC 55-139 10/09 23:30
Striping / Marking 10/10 04:01
5 NB/SB #2 2 NB OFF TO JUNIPERO SERRA - SB OFF TO JUNIPERO SERRA 10/09 21:01
Paving 10/10 05:01
5 SB #1, #2, #3 3 SB ON ARTESIA AVE - JCT 91 / 5 SEP OH 55-502R 10/09 23:01
Bridge Work 10/10 04:01
5 SB #1, #2 2 SB ON FR BEACH BLVD - SB ON FR BEACH BLVD 10/09 23:01
K-Rail 10/10 05:01
5 SB #1, #2 2 SB OFF TO BEACH BLVD - SB OFF TO BEACH BLVD 10/09 23:01
K-Rail 10/10 05:01
5 SB #1, #2 2 SB OFF TO RED HILL AVE - SB OFF TO RED HILL AVE 10/09 22:01
Bridge Work 10/10 04:01
5 SB #3, #4, #5 5 FIRST STREET OC 55-174 - END BR 55-655 10/09 23:01
Bridge Work 10/10 04:01
5 SB #1, #2 2 SB ON ARTESIA AVE - SB ON ARTESIA AVE 10/09 23:01
K-Rail 10/10 05:01
5 SB #1, #2 2 SB ON FR FIRST STREET - SB ON FR FIRST STREET 10/09 22:01
Bridge Work 10/10 04:01
22 WB #2 3 EB OFF BRISTOL/LA VETA - EB OFF BRISTOL/LA VETA 10/09 22:15
Street Rehab 10/10 05:15
39 NB/SB #1, #2, #3 4 SLATER AVE Lanes 1, 2, 4; 200 ft away from intersection - SLATER AVE Lanes 1, 2, 4; 200 ft away from intersection 10/09 22:01
Electrical Repair 10/10 05:01
57 SB #1, #2 2 SB ON LAMBERT RD - LAMBERT RD UC 55-492 10/09 21:01
Paving 10/10 05:01
57 SB #1, #2 2 SB OFF LAMBERT RD - SB OFF LAMBERT RD 10/09 21:01
Paving 10/10 05:01
73 NB #2 3 JCT 73/405 - JCT 73/405 10/09 22:01
Other check Remarks 10/10 05:01
90 EB/WB #1, #2, #3 2 RANDOLPH AVE LT - HARBOR BLVD 10/09 22:01
Grinding 10/10 05:01
91 WB #1, #2 2 WB 91 CONNECTOR TO NB RTE 5 - WB 91 CONNECTOR TO NB RTE 5 10/09 23:01
Bridge Work 10/10 04:01
261 SB #1, #2 2 SB ON FR TOLL PLAZA - SB ON FR TOLL PLAZA 10/09 21:01
Marker Replacement 10/10 05:01
261 SB #1, #2 2 JCT RTE 241 - BEGIN RTE AT WALNUT OC 10/09 21:01
Marker Replacement 10/10 05:01
261 SB #1, #2 2 SB ON FR SANTIAGO CNYN - SB ON FR SANTIAGO CNYN 10/09 21:01
Marker Replacement 10/10 05:01
261 SB #1, #2 2 SB ON FR IRVINE BLVD - SB ON FR IRVINE BLVD 10/09 21:01
Marker Replacement 10/10 05:01
405 NB #1, #2, #3 3 SB ON SEG FR FAIRVIEW Harbor/Susan St Off Ramp - SB OFF TO FAIRVIEW RD 10/09 22:01
Other check Remarks 10/10 05:01
405 NB #4, #5, #6 8 SB ON SEG FR FAIRVIEW - SB OFF TO FAIRVIEW RD 10/09 22:01
Other check Remarks 10/10 05:01


DAY CLOSURES FRIDAY 10/10/2008 [18 Closures Found]
Rte Dir Lanes
Closed
Total
Lanes
Begin - End Location/
Type of Work
Closure
Period
1 NB/SB #2 2 EMERALD BAY ENT #1&2 - EMERALD BAY ENT #7 LT 10/10 09:01
Sewer Repair 10/10 15:01
1 SB #2 2 5TH AVE RT - 8TH AVE RT 10/10 09:01
Move Equipment 10/10 15:01
5 EB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/10 09:01
Tree Trimming 10/10 15:01
5 EB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/10 09:01
Tree Trimming 10/10 15:01
5 N/A #3 3 OSO PARKWAY OC 55-509 - OSO PARKWAY OC 55-509 10/10 09:01
Other check Remarks 10/10 15:01
5 NB/SB #1 2 NB OFF TO JUNIPERO SERRA - SB OFF TO JUNIPERO SERRA 10/10 09:01
Paving 10/11 05:01
5 SB #1 2 SB OFF HOV TO GENE A WAY - SB ON HOV FR GENE A. WAY 10/10 09:01
Tree Trimming 10/10 15:01
5 SB #1 2 SB OFF HOV TO GENE A WAY - SB ON HOV FR GENE A. WAY 10/10 09:01
Tree Trimming 10/10 15:01
5 WB #3 3 NB ON FR SAND CYN AVE - SB OFF TO SAND CYN AVE 10/10 09:15
Other check Remarks 10/10 15:15
5 WB #1 2 NB ON HOV FR GENE A WAY Gene Autry State College - SEG NB OFF HOV TO GENE WY Gene Autry to I-5 10/10 09:01
Tree Trimming 10/10 15:01
22 EB #2 2 JCT 5 - EB OFF TO NB 5 / NB 57 10/10 09:01
Other check Remarks 10/10 14:01
39 NB/SB #1, #2, #3 3 ROSECRANS AVE - IMPERIAL HWY (RTE 90) 10/10 09:01
Other check Remarks 10/10 15:30
39 SB #1 3 ATLANTA AVE - JCT ST 1 10/10 09:15
Move Equipment 10/10 15:15
55 EB/WB #1 4 Slope Paving at Paularino - Slope Paving at Paularino 10/10 09:01
Bridge Work 10/10 14:01
57 SB #1 3 SB OFF LAMBERT RD - SB OFF LAMBERT RD 10/10 08:01
Paving 10/10 15:01
57 SB #1 3 END BR 55-492 - SB ON LAMBERT RD 10/10 08:01
Paving 10/10 14:01
57 SB #2 2 SB ON LAMBERT RD - LAMBERT RD UC 55-492 10/10 08:01
Drainage 10/10 15:01


NIGHT CLOSURES FRIDAY 10/10/2008 [21 Closures Found]
Rte Dir Lanes
Closed
Total
Lanes
Begin - End Location/
Type of Work
Closure
Period
1 NB #1 2 NB OFF TO DOHENY PK RD - DEL OBISPO ST 10/10 20:30
Paving 10/11 05:30
5 NB #1 1 NB ON FR ORANGETHORPE AV - NB ON FR ORANGETHORPE AV 10/10 23:01
Electrical Repair 10/11 05:01
5 NB #1 1 NB ON FR MANCHESTER / BCH - NB ON FR MANCHESTER / BCH 10/10 23:01
Electrical Repair 10/11 05:01
5 NB #1, #2, #3 3 JCT 91 / 5 SEP OH 55-502R - ARTESIA AVE UC 55-139 10/11 00:30
Striping / Marking 10/11 05:01
5 NB #1, #2, Left HOV 5 BROOKHURST ST OC 55-89R - JCT 91 / 5 SEP OH 55-293L 10/10 22:01
Bridge Work 10/11 05:01
5 NB #1 1 NB OFF TO BEACH / MNCHTR - NB OFF TO BEACH / MNCHTR 10/10 23:01
K-Rail 10/11 05:01
5 NB #1 1 NB OFF TO BEACH / MNCHTR - NB OFF TO BEACH / MNCHTR 10/10 23:01
K-Rail 10/11 05:01
5 NB/SB #2 2 NB OFF TO JUNIPERO SERRA - SB OFF TO JUNIPERO SERRA 10/10 21:01
Paving 10/11 05:01
5 SB #1, #2, #3 3 SB ON ARTESIA AVE - JCT 91 / 5 SEP OH 55-502R 10/11 00:01
Bridge Work 10/11 05:01
5 SB #1, #2 2 SB ON FR BEACH BLVD - SB ON FR BEACH BLVD 10/10 23:01
K-Rail 10/11 05:01
5 SB #1, #2 2 SB ON ARTESIA AVE - SB ON ARTESIA AVE 10/10 23:01
K-Rail 10/11 05:01
22 WB #2 3 EB OFF BRISTOL/LA VETA - EB OFF BRISTOL/LA VETA 10/10 22:15
Street Rehab 10/11 05:15
39 NB/SB #1, #2, #3 4 SLATER AVE Lanes 1, 2, 4; 200 ft away from intersection - SLATER AVE Lanes 1, 2, 4; 200 ft away from intersection 10/10 22:01
Electrical Repair 10/11 05:01
57 SB #1, #2 2 SB ON LAMBERT RD - LAMBERT RD UC 55-492 10/10 21:01